Year 45 CDBG Project

Year 45 CDBG Project

The project includes the 8-inch replacement of approximately 300 linear feet of sanitary sewer line by pipe enlargement methods along the 1400 Block of South Cherry Lane from Downe Drive to Tumbleweed Trail.

PROJECT BEGINNING: FEBRUARY 2020
ESTIMATED PROJECT COMPLETION: MAY 2020

map showing area where a sewer line is being worked on

ENGINEERING DIAGRAM 

PROJECT UPDATES

Feb 10 2020: Contractor setting up traffic control devices in preparation for construction beginning this week
Feb 11 2020: Contractor delivered equipment to project area
Feb 21 2020: Manholes have all been poured. Sewer line replacement will begin next week
Mar 6 2020: Sewer line is installed with manholes, awaiting video and vacuum testing