Clifford Street Sewer and Paving Project

Clifford Street Sewer and Paving Project

New sewer lines are being installed along Clifford Street from Bomber Road to Cherry Lane. Once the new sewer lines are in place, the street will be reconstructed with all new materials. Clifford will remain open for the duration of the project but there will be alternating lane closures during the course of the project. There may be a few days where detours are utilized. 

PROJECT BEGINNING: JANUARY 2020
ESTIMATED PROJECT COMPLETION: FEBRUARY 2021
CONTRACTOR: RELIABLE PAVING
PROJECT MANAGER: ERIC WORLEY

photo of clifford street from Bomber Rd looking east

Clifford Project Map

CLIFFORD STREET PHASE ONE TRAFFIC CONTROL PLAN
CLIFFORD STREET PHASE TWO TRAFFIC CONTROL PLAN
CHERRY LANE TRAFFIC CONTROL PLAN
FULL PROJECT SCHEDULE

PROJECT UPDATES

Jan 22 2020: Open public meetings held at Union Hall so residents and interested parties could speak with Public Works and Contractor and ask questions/get information about the project
Jan 23 2020: Materials and equipment delivered to the project zone
Jan 29 2020: First section of pipe for the project laid at Bolliger & Smith St (PICTURE)
Jan 30 2020: About 80 feet of pipe laid (PICTURE)
Feb 3 2020: 60 feet of pipe laid from manhole station 0+00 to within 25 feet of station 2+00. Excavation has begun for manhole installation at station 2+00. Compaction and backfilling is also in process for the first 60 feet of pipe that has been laid. (PICTURE)
Feb 7 2020: 320 feet of pipe laid, second manhole station installed. Work progressing ahead of schedule
Feb 13 2020: Saw cut across Harwell Street starting. Traffic being re-routed in the area
Feb 21 2020: Project has reached Clifford Street. Traffic control devices being placed as Westbound portion of project set to begin on Monday
Feb 28 2020: Work is progressing as contractor is digging near the Clifford/Cherry Lane intersection. Please follow cones, signs and direction of on-site traffic control personnel when you travel through the area
Mar 6 2020: Sewer line installation continuing west down Clifford. 2000 feet of new line installed during the project so far.


If you have any questions or concerns regarding this project, please contact Project Manager Eric Worley at eworley@wstx.us