- ESTABLISHED IN 1849 -

 Farmers Branch Creek Project

home    contact us


 

FARMERS BRANCH FLOOD REDUCTION PROJECT
From the Office of the City Manager, Linda Ryan
How the City of White Settlement got to where we are today!

The Flood in June 2000 encouraged the City of White Settlement to continue their request for assistance from the Corps of Engineers to construct a Federal Flood Damage Reduction Project along Farmers Branch.  More than 100 homes and businesses have experienced flooding in 2000 and again in 2004.  In October 2001, the cost-share agreement for a feasibility study was presented to the Federal Government realizing that the “engineering and fact finding” efforts would not be visible for several years. In 2005, the voters approved a $6.15 M bond, which was thought at the time to be the City’s share of the project.  There was a moratorium put in place on Federal funding which wasn’t lifted until 2007In April 2008, the Corps of Engineers met with the City Council to discuss the Design and Construction of Farmers Branch.  At this time, the City’s estimated share was $10.5 M with the total project being $16.2 M.  The Council discussed issuing an additional $4 M Certificates of Obligations realizing the $6.15 M approved by the voters in 2005 would not be sufficient.  In May 2009, the $6.15 M bond was issued and funding received.  The 100% Design Plan was approved by the City Council in February 2010.  Today, (June 2011), the reality is here.  The City’s share is now estimated to be more than $11 M with total project over $18 M.  Federal funding is maxed out at $7 M.  The City Council met in a workshop on June 7th and again on June 14th to consider and approve additional debt to complete the Flood Project.  Funding must be in place prior to awarding the Construction Bids.

The “Project” is the Locally Preferred Plan which provides protection for the 100-year flood event for the majority of the residents.  This plan from the US Army Corps of Engineers prepared by Halff and Associates is composed of channel improvements to Farmers Branch Main Stem and the Las Vegas Trail Tributary.  Bridges will be replaced at Meadow Park, Las Vegas Trail and George Street.  The existing bridge at Mirike will remain in place.  The bridge at Pemberton Street will be demolished but not replaced.

26 houses were purchased and demolished, residents were relocated.  The sanitary sewer interceptor that ran the length of the channel has been moved which will enable the flowline of the channel to be lowered.  The easements needed from 88 Parcels have been purchased and fences, trees, and sheds will soon be moved.  Utilities are ready to be relocated as construction bids are scheduled to be awarded in August 2011. 

 

Revenues:

 

Federal Funding Balance (Spent $1,890,187)

$   4,603,967

City - 2009 Bond Proceeds

  6,143,177

Balance of Non Federal (% Design)

401,723

City - Reserves from Prior Tax Notes & Interest

     366,573

 Sub-total revenues

$11,515,440

 

Actual & Estimated Expenditures:

 

Corp of Engineers (% Design)

$       515,000

Property, Demolitions, Relocation, Incidental Expense

 2,501,827

Parcels & Buyouts of Easements

 408,339

Utilities Relocation

 1,280,747

Condemnation Expenses

         71,995

Engineering, Surveys, Waterline Replacement

    339,847

Acquisitions, Appraisals, Negotiation Services, etc.

    854,000

Sub-total (city) expenditures

 $   5,971,755

 

 

Estimated Construction Cost of Project

$ 11,280,872

 

 

Total expenditures

$ 17,252,627

Estimated Shortage

($ 5,737,187)

     

 

 

 

 


2005 Copyright